Scope:

Rendered civil and structural works comprising furnace foundation, 4-poster structure, equipment foundation, roads, railway tracks, drawing and sewerage. Utilities and auxiliaries comprised off furnace cooling system, compressed air, nitrogen, steam, oxygen for blast furnace proper, gas cleaning plant, cast house, bell-less top charging system, stove valve cooling, air-conditioning and ventilation systems.

  • Value Additions:
  • The plant construction and commissioning was been done in a record time and in line with international stand. Innovative engineering solutions: Design and engineering of 4-poster structure thereby eliminating the need for pouring concrete into the hollow structures Engineered sequence of installation of the down comer connecting blast furnace and gas cleaning plant Blast furnace foundation was designed, critically examined and approvals for construction procured to suit site conditions such that no re-engineering was called for. Design/Engineering of systems and sub-systems were critically examined to enable problem-free construction. Design inputs from various agencies were compiled and integrated in design for construction in record time. State-of-the-art safety solutions were provided in design, basic engineering inputs, operational maintenance, extensive fire fighting systems, fire detection systems were incorporated and gratings were provided to ensure accident-free operations. The innovations, safety measures and timely delivery provided cost efficiencies to the client