FEW PROJECT HIGHLIGHTS























                                TCS Sahyadri PARK 2 - WELCOME BLOCK



             CS Sahyadri PARK 2 was initiated in June 2019 by   Extended Monsoons
             Harshal Buildcon. The welcome block being an
        Tincubation centre for TCS was required to start      Challenges - Monsoons in 2019 extended up to
        the operations early given the SEZ compliance and     Sept, which affected the site activities with abysmal
        generate revenue before February 2020. TCE's scope    productivity.
        as a PMC was to maintain Safety, Quality and Timelines
        for all activities such as Excavation, RCC, MS erection,   Solution - The activity was not stopped, and the
        Civil works, Decking, Façade, HVAC & Electrical HS & LS,   Vendor deployed additional resources to continue
        STP, Access control, CCTV, DG, UPS, Finishing, Interiors,   working relentlessly even during heavy rainfall.
        Statutory compliance and Handover.                    Planning and readiness to work in dry spell expedited
                                                              the activity resulting in minimising the delay.
        Harshal Buildcon being a developing company,
        required hand-holding and guidance in safety, quality,   Value additions:
        scheduling, project tracking and billing at all project
        cycle levels adding to the challenge of achieving the       Project completion within allotted Budget even
        project commitments.                                     after cost implications.

        Following are few of the unforeseen challenges in detail       Reduction in PCC thickness
        and how they were dealt with to complete the project       Approaching sub-vendors for expediting the
        before time and cost-saving.
                                                                 procurement and execution processes.

        Excavation & Backfilling                                  Close monitoring and daily tracking at all the fronts.

        Challenges - The soil at the welcome block area was       MS shuttering for increasing productivity.
        Black cotton. The required depth for excavation as per
        drawing and borehole data was avg. 2m. However, due       Blockwork in place of shuttering for expediting
        to the huge quantity of black cotton soil and dumped     concreting activity.
        garbage from around the area, the required strata were
        encountered only after 7m of excavation resulting         Plumb concrete in place of backfilling for
        in timeline delay and cost implications of 1.06 Cr for   expediting PCC works.
        excavation and backfilling.
                                                                  Hilti- cleat and lock anchor, HSUR arrangement for
        Solution - Majorly available moorum from inside the      dry cladding, reducing time & cost.
        premises was used for saving time and cost. Additional
        resources were deployed for expediting the activity.







                                                                                               Sept - Dec 2020   63