           A PROJECT
           Rourkela Smart City



           Building on its steel foundation, natural setting and
           cosmopolitan character, Rourkela will be an inclusive,
           sustainable and self-reliant city propelling regional
           economic development with best-class infrastructure. There
           are 23 projects taken under Rourkela Smart City, including
           Smart Road, Citizen Friendly Parks, Football Stadium, Indoor
           Stadium, Auditorium, Museum, Command Control Centre,
           Pond Beautification, River Side Beautification, Smart Vending
           Zones, Smart Parking, Market Complexes etc.

           CHALLENGES
           All significant projects like Birsa Munda Football Stadium,
           Smart Road, Biju Patnaik Indoor Stadium, Rourkela One
           started after the lockdown period in April 2020. The projects
           continue their progress with all due diligence as per plan
           with no impact on the original completion date. The project
           team has adopted the latest technologies like Post Stressed
           Concrete, Lean Technology, Slip Form type Form work for
           Precast work to expedite the work progress. As the city is
           ancient, retrofitting all the roads is very challenging. Due
           to the existing utilities in the ROW and densely populated
           area, the project team overcame all challenges to execute
           as planned and ensure proper traffic management. Other
           challenges include Encroachments, Multi-level approvals,
           Rehabilitation, High traffic, Low traffic management, Multiple
           players on the same site, Unorganised existing services and
           Variable Soil Strata, which we overcame with some strategic
           planning and sound engineering solutions.
                                                              work as we used slip form shuttering at the precast yard. In
           TECHNOLOGIES                                       continuation to above, we also took necessary care to avoid
           Technologies and effective way of working were the reason.   Kota finishing in sitting areas of the stadium by replacing the
           We could achieve our targets. In Birsa Munda Stadium, using   same with an excellent precast finish, thus saving cost and
           Post Stressed Technology, we reduced our concrete work   time. The project team has taken due diligence to achieve
           and de-shuttering time considerably. Also, taking benefit   targets by adopting such equipment that was not considered
           of Lean Processes, we reduced logistic time for material   earlier, like the Pile Rig machine for piling work and saved
           movement. We saved considerable time in precast concrete   considerable time lost due to COVID-19.